According to foreign media reports on February 12, Jinshi Data stated that the largest power grid in the United States has received federal government approval to expedite the review of dozens of new power plant projects in response to increased demand due to the surge in artificial intelligence data centers. The Federal Energy Regulatory Commission announced in an order released later on Tuesday that PJM Interconnection LLC, which manages the network spanning 13 states from the East Coast to Chicago, will begin reviewing up to 50 new projects starting in April. These projects will be specifically aimed at enhancing grid reliability to help avoid potential power shortages by the end of this decade
The largest power grid in the United States has been approved to review dozens of new power plant projects