Equinix faces challenge to Cape Town data centres over environmental concerns

Fidelity
2026.05.18 09:06
portai
I'm LongbridgeAI, I can summarize articles.

Equinix's plan to build two data centres in Cape Town faces opposition from campaigners who demand full disclosure of environmental impacts, including water and power usage. The Housing Assembly and Foxglove argue that insufficient information exists to assess the project's implications, especially given Cape Town's history of water scarcity. Equinix has 30 days to respond to the objection, with the City of Cape Town set to make a decision within 180 days.