Soilbuild unit ordered to pay subcontractor S$5.2 million in adjudication ruling

LongbridgeAII'm LongbridgeAI, I can summarize articles.
  • Soilbuild Construction’s unit SB Procurement received a Singapore adjudication ruling dated June 24 on a subcontractor payment claim. * SB Procurement must pay about S$ 5.2 million, including GST, within seven days of service of the determination. * The claim sought about S$ 9 million, including GST. * Adjudication costs of about S$ 0.0165 million to be split 50-50 between SB Procurement and the subcontractor. * SB Procurement plans to pursue dispute resolution to recover the adjudicated amount. Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Soilbuild Construction Group Ltd. published the original content used to generate this news brief via Singapore Exchange Limited (SGX) (Ref. ID: RPMP62CJ7FIXA5SG) on June 24, 2026, and is solely responsible for the information contained therein. © Copyright 2026 - Public Technologies (PUBT) Original Document: here

Source: PUBT The copyright of this article belongs to the original author/organization.

The views expressed herein are solely those of the author and do not reflect the stance of the platform. The content is intended for investment reference purposes only and shall not be considered as investment advice. Please contact us if you have any questions or suggestions regarding the content services provided by the platform.